1817 Silliman St
San Francisco permit 202512161933 · Excelsior
Demolish (e) type v 2-story single family residence.
- Filed
- Jan 3, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 20 stops across 6 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2025 | Jan 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2026 | May 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2026 | Jun 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jul 31, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2026 | May 31, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | Jun 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 28, 2026 | Jul 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 12, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | May 28, 2026 | Oct 15, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jul 20, 2026 | Jul 30, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 31, 2026 | Aug 31, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 1, 2026 | Sep 2, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 1, 2026 | Sep 1, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2026 | Sep 3, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 1, 2026 | Sep 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 14, 2026 | Sep 14, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Sep 14, 2026 | Sep 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 25, 2026 | Sep 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2026 | Sep 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Triage
- Estimated cost
- $10,188
| Name | Role | License on permit |
|---|---|---|
| Riyad N Ghannam Rg-Architecture | Architect | C-29116 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022