345 10th Av
San Francisco permit 202512161942 · Inner Richmond
Horizontal & vertical addition. total 1035 sq. ft. including new kitchen & new 3rd floor with 1 bedroom, 2 baths, office & playroom.
- Filed
- Jan 6, 2026
- Issued
- Oct 15, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2025 | Jan 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 6, 2026 | Jan 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 8, 2026 | Feb 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2026 | Feb 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 8, 2026 | Feb 27, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2026 | Feb 4, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 8, 2026 | Jan 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2026 | Jan 12, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 8, 2026 | Feb 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Jan 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 8, 2026 | Sep 4, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2026 | Feb 27, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | Apr 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2026 | May 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2026 | Jun 11, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Jul 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 20, 2026 | Jul 20, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 20, 2026 | Jul 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2026 | Aug 5, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Jul 31, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Aug 5, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2026 | Aug 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Oct 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Linnea Holbrook Clark Studio Nea | Payor | C37079 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025