Addition (type unconfirmed)Full plan reviewIssued
Street view · Dec 2020
Google Street View of 22 Whitney St, Dec 2020
Scope of work
As written on the permit application.

Installation of a 3-stop residential elevator. reconfiguration of front roof structure & conversion of attic space into 3rd floor living space including a bathroom.

Timeline
Key dates from the city record.
Filed
Jan 6, 2026
Issued
May 26, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
3 times, by Building Inspection
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 6, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 8, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 10, 2026Approved

Building plan review

Building Inspection · BLDG

Feb 22, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 23, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jan 30, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 24, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 21, 2026Approved

Permit Processing Center

Building Inspection · PPC

Apr 30, 2026Administrative

Zoning review

Planning · CP-ZOC

Mar 25, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 3, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 7, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 1, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 1, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 13, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 20, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 10, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 13, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 20, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 23, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 30, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 23, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 29, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 26, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$220,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Shawn Michael FritzArchitectC-29770
Donald David

Double D Engineerisgn

Engineer3928
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512171981 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record