46 Saint Germain Av
San Francisco permit 202512172047 · Twin Peaks
New skylight and bathroom enlargement.
- Filed
- Jan 8, 2026
- Issued
- May 18, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 17, 2025 | Dec 17, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2025 | Jan 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2026 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Mar 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Mar 10, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Feb 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 30, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | Apr 10, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 30, 2026 | Apr 1, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 30, 2026 | Apr 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2026 | Apr 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 3, 2026 | Apr 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2026 | Apr 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 10, 2026 | May 18, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican & Mosey Architects | Architect | C31398 |
| Daniel Polivka Holmes | Engineer | C79948 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025