1969 10th Av
San Francisco permit 202512172050 · Inner Sunset
Interior remodel within e building envelope. new livable space 1st fl level space 1st level, new storage loft over garage. new stair btwn floors. new elec plumb as req at area of remodel. replace windows in kind w new dbl glazed. 1 new fire rated window. new deck at grade, 4 new skylights
- Filed
- Dec 17, 2025
- Issued
- Feb 25, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Once, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 17, 2025 | Dec 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 17, 2025 | Dec 17, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 17, 2025 | Dec 17, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 9, 2026 | Jan 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2026 | Jan 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 9, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2026 | Jan 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2026 | Jan 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2026 | Feb 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Leslie Carlene Arnold Leslie Arnold Architect | Architect | C23246 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026