As written on the permit application.

Abatement of nov# 202183573 and planning enforcement 2023-010000enf. seeking density exception for fourplex in rh-1. legalize three unpermitted units at basement (unit a), 1/f (unit b) and 3/f (unit d). interior legalization of as-built kitchens, bedrooms, living areas and baths. limited rear exteri

Timeline
Key dates from the city record.
Filed
Feb 26, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 6 departments
Comments issued
6 times, by Permit Center, Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 2, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 4, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 27, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 8, 2026Approved

Address verification

Building Inspection · ADDR

Mar 25, 2026Not Applicable

Building plan review

Building Inspection · BLDG

Mar 12, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 24, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 12, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 6, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 17, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 14, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 9, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Fire prevention review

Fire Department · SFFD

In progress—

Urban forestry

Public Works · DPW-BUF

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Thomas Steven Podesta

Thomas Podesta Engineer

ArchitectC37028
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512172065 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record