505 Mission Rock St
San Francisco permit 202512172072 · Mission Bay
Phase ii: mayoral ed 17-02 & 13-01: erect type i-a, a 23-story with 233 residential units with 2-stories above-grade parking.
- Filed
- Feb 6, 2026
- Issued
- Sep 9, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 61 stops across 7 departments
- Comments issued
- 11 times, by Permit Center, Redevelopment, Fire Department, Public Works, Public Utilities, Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 15, 2025 | Jan 6, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 19, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2026 | Feb 6, 2026 | Administrative |
Redevelopment review Redevelopment · REDEV | Feb 6, 2026 | Feb 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2026 | Mar 13, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 6, 2026 | Mar 14, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2026 | Feb 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 6, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2026 | Feb 19, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 6, 2026 | Feb 19, 2026 | Approved |
Public Health HEALTH-HM | Feb 6, 2026 | Feb 9, 2026 | Approved |
Public Health HEALTH-MH | Feb 6, 2026 | Feb 10, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 6, 2026 | Sep 3, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 2, 2026 | Apr 1, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Mar 19, 2026 | Mar 19, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 27, 2026 | Apr 2, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 9, 2026 | Jun 14, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 23, 2026 | Jun 23, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 26, 2026 | Jun 11, 2026 | Approved |
Redevelopment review Redevelopment · REDEV | Jul 27, 2026 | Aug 26, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Jul 31, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 5, 2026 | Aug 5, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2026 | Aug 14, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2026 | Aug 11, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 14, 2026 | Aug 14, 2026 | Approved-Stipulated |
Address verification Building Inspection · ADDR | Aug 17, 2026 | Aug 17, 2026 | Administrative |
Public Utilities programs review Public Utilities · SFPUC-PRG | Aug 17, 2026 | Aug 17, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Aug 19, 2026 | Aug 19, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 20, 2026 | Approved |
Public Health HEALTH-HM | Aug 28, 2026 | Aug 31, 2026 | Approved |
Public Health HEALTH-MH | Aug 28, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2026 | Sep 9, 2026 | Administrative |
Addendum 1: Piles
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2026 | Sep 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 18, 2026 | Sep 18, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 18, 2026 | In progress | In Progress |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2026 | Oct 26, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Sep 18, 2026 | Sep 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2026 | Sep 24, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Sep 18, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2026 | Sep 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2026 | Sep 23, 2026 | Administrative |
Address verification Building Inspection · ADDR | Sep 23, 2026 | Sep 30, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2026 | Sep 30, 2026 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Sep 23, 2026 | In progress | Administrative |
Building plan review Building Inspection · BLDG | Oct 2, 2026 | Oct 7, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 19, 2026 | Oct 23, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Foundation | superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 22, 2026 | Oct 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2026 | Oct 1, 2026 | Administrative |
Address verification Building Inspection · ADDR | Oct 9, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Oct 9, 2026 | Oct 28, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Oct 9, 2026 | Oct 16, 2026 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Oct 9, 2026 | Nov 2, 2026 | Not Applicable |
Public Health HEALTH-MH | Oct 9, 2026 | Oct 14, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 9, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 4: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 2, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $67,250,000
| Name | Role | License on permit |
|---|---|---|
| Yakuh Django Askew Y.A. Studio | Architect | C29776 |
| Joe Gulden Imeg | Engineer | S-5797 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026