530 Jackson St
San Francisco permit 202512172080 · Chinatown
B lvl & 1 lvl: new base building room, restaurant spaces and circulation spaces constructed. lvl 2,3 & n/s 4: new b occ. office spaces provided. s/s lvl 4 and lvl 5: new residential units to be provided. (e) ter lvl 5 renovated and doors to ter replaced with sliding door system with egress door.
- Filed
- Jan 23, 2026
- Issued
- Aug 6, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Fire Department, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 16, 2025 | Jan 2, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 5, 2026 | Jan 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2026 | Jan 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2026 | Mar 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 23, 2026 | Feb 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 23, 2026 | Feb 2, 2026 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2026 | Feb 3, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jan 23, 2026 | Feb 12, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2026 | Feb 4, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Jan 23, 2026 | Jan 27, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jan 23, 2026 | Aug 4, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 20, 2026 | Mar 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 20, 2026 | Feb 23, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 20, 2026 | Feb 24, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Feb 20, 2026 | Feb 27, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 10, 2026 | Mar 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2026 | Apr 23, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2026 | Apr 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2026 | Apr 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 14, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2026 | Apr 17, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Apr 10, 2026 | Apr 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2026 | Apr 20, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 23, 2026 | May 11, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 1, 2026 | May 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2026 | Jun 11, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 9, 2026 | Jun 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 10, 2026 | Jun 17, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 12, 2026 | Jul 21, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Jun 12, 2026 | Jun 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 22, 2026 | Jun 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Jul 31, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 3, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Jul 31, 2026 | Jul 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 3, 2026 | Aug 3, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 3, 2026 | Aug 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2026 | Aug 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $4,323,223
| Name | Role | License on permit |
|---|---|---|
| Carrie E Byles Studio K | Architect | C-27689 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026