1021 Cole St
San Francisco permit 202512182133 · Haight Ashbury
Partial remodel with attached single car garage. partial demolition of (e) lower floor slab & construction of 355 sf of unconditioned space to habitable area. addition of 4 roof dormers & a skylight. remodel (e) rear deck & new 72 sf deck @ 4th floor level.
- Filed
- Jan 7, 2026
- Issued
- Jul 1, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 16, 2025 | Jan 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2025 | Jan 7, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2026 | Jan 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 7, 2026 | Feb 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 7, 2026 | Feb 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 7, 2026 | Jan 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 7, 2026 | Jan 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2026 | Jan 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 7, 2026 | Jun 17, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 2, 2026 | Feb 2, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2026 | May 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jun 1, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 28, 2026 | Jun 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 28, 2026 | Jun 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 4, 2026 | Jun 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 4, 2026 | Jun 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2026 | Jun 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2026 | Jun 17, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2026 | Jul 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $760,000
| Name | Role | License on permit |
|---|---|---|
| Mark David English Mark English Architects | Architect | C18594 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025