2180 Folsom St
San Francisco permit 202512182161 · Mission
Interior build out on an industrial warehouse space after fire repair. fire repair permit has been closed out. work includes new; non-structural partitions, plumbing distribution, electrical, mechanical, lighting replacement, insulated penthouse assembly, pedesal rooftop mechanical deck.
- Filed
- Dec 18, 2025
- Issued
- Feb 17, 2026 (2 months after filing)
- Completed
- Sep 23, 2026 (7 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- Twice, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 18, 2025 | Dec 18, 2025 | Administrative |
Code enforcement Building Inspection · CES | Dec 18, 2025 | Dec 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2025 | Dec 18, 2025 | Issued Comments |
Intake Building Inspection · INTAKE | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2025 | Dec 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2025 | Feb 6, 2026 | Approved-Stipulated |
Intake Building Inspection · INTAKE | Jan 6, 2026 | Jan 6, 2026 | Administrative |
Intake Building Inspection · INTAKE | Jan 7, 2026 | Jan 7, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 7, 2026 | Jan 7, 2026 | Approved |
Intake Building Inspection · INTAKE | Feb 6, 2026 | Feb 6, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Feb 6, 2026 | Feb 6, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 6, 2026 | Feb 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 6, 2026 | Feb 6, 2026 | Not Applicable |
Intake Building Inspection · INTAKE | Feb 9, 2026 | Feb 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 9, 2026 | Feb 9, 2026 | Not Applicable |
Code enforcement Building Inspection · CES | Feb 10, 2026 | Feb 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2026 | Feb 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2026 | Feb 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2026 | Feb 13, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2026 | Feb 13, 2026 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2026 | Feb 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 17, 2026 | Feb 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $232,965
| Name | Role | License on permit |
|---|---|---|
| Hallie Chen Caha Design Group | Architect | C38753 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026