505 Diamond St
San Francisco permit 202512192237 · Noe Valley
Construct basement wall and make crawlspace area habitable with new bedroom, bathroom, family room, and laundry. excavation and new retaining walls. rebuild back deck to new concrete deck.
- Filed
- Apr 23, 2026
- Issued
- Oct 6, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 27 stops across 4 departments
- Comments issued
- 9 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Feb 25, 2026 | Mar 9, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 2, 2026 | Apr 14, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2026 | Apr 23, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Apr 23, 2026 | Oct 5, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 24, 2026 | Apr 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 29, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2026 | May 29, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2026 | May 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | May 6, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 21, 2026 | Jul 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 21, 2026 | Jul 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2026 | Jul 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 21, 2026 | Jul 28, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 4, 2026 | Aug 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 4, 2026 | Aug 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 4, 2026 | Aug 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 4, 2026 | Aug 7, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 11, 2026 | Aug 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2026 | Aug 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 11, 2026 | Aug 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2026 | Oct 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 30, 2026 | Oct 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 30, 2026 | Oct 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 30, 2026 | Oct 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 30, 2026 | Oct 5, 2026 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $401,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey Fitch Sfa Design Group Llc | Engineer | C64889 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019