535 Pacific Av #0
San Francisco permit 202512192277 · Chinatown
Ext envelope,door and enclosure improvements.replace (3) main entrance doors, aluminum, steel fire-rated windows. replace (2) (e) skylights and add (1) new skylight, new shaft enclosure adj to stair enclosure at roof . retrofit (4) ext balconies, including installation of (n) metal guardrails.
- Filed
- Jan 14, 2026
- Issued
- Aug 18, 2026 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2025 | Jan 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 14, 2026 | Jan 14, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 14, 2026 | Mar 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 14, 2026 | Mar 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2026 | Feb 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 14, 2026 | May 5, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 14, 2026 | Jul 30, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2026 | Feb 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 2, 2026 | Mar 11, 2026 | Administrative |
Electrical plan review Building Inspection · MECH-E | Mar 11, 2026 | Mar 19, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 13, 2026 | Mar 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 13, 2026 | Apr 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2026 | Jun 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 29, 2026 | Jun 29, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 15, 2026 | Jul 16, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 22, 2026 | Jul 22, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 22, 2026 | Jul 27, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jul 22, 2026 | Jul 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 22, 2026 | Jul 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2026 | Aug 18, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $293,847
| Name | Role | License on permit |
|---|---|---|
| Kris Wallace Johnson Gfds Engineers | Engineer | S 4319 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026