100 California St
San Francisco permit 202512192291 · Financial District/South Beach
1st floor: new fidelity investment center. new partitions and office, new ducts, power, & lighting.
- Filed
- Dec 19, 2025
- Issued
- Feb 17, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- Once, by Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 22, 2025 | Dec 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 23, 2025 | Dec 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2026 | Jan 9, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 9, 2026 | Jan 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2026 | Feb 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 3, 2026 | Feb 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2026 | Feb 3, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Feb 17, 2026 | Feb 17, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 17, 2026 | Feb 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,134,601
| Name | Role | License on permit |
|---|---|---|
| Robert Eric Smith Smithworks Engineering | Architect | S5679 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026