651 Cole St #0
San Francisco permit 202512192292 · Haight Ashbury
Other (type unconfirmed)Over-the-counter, with plansComplete
Scope of work
As written on the permit application.
Remove two (e) front balconies and replace with (e) patio doors with new windows within the same opening.
Timeline
Key dates from the city record.
- Filed
- Dec 19, 2025
- Issued
- Feb 3, 2026 (2 months after filing)
- Completed
- Apr 24, 2026 (3 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
- Review stops
- 8 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 19, 2025 | Dec 19, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2025 | Dec 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2025 | Dec 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2025 | Dec 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2025 | Dec 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2025 | Dec 19, 2025 | Approved |
Apartment and hotel inspection Building Inspection · HIS | Feb 3, 2026 | Feb 3, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2026 | Feb 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
Permit details
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $15,000
People named on this permit
Only people we matched to a California license are listed.
| Name | Role | License on permit |
|---|---|---|
| Kevin Ka-Kiu Ma | Architect | c29781 |
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512192292 on the city's permit tracking site
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025