3516 Clay St
San Francisco permit 202512192311 · Presidio Heights
Horizontal addition of (e) building footprint, includes full remodel associated in scope of work.
- Filed
- Dec 19, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 33 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Works, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2025 | Jan 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2025 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Feb 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Feb 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Feb 27, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Feb 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 21, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 14, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Jan 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Feb 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Feb 27, 2026 | Feb 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Mar 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 14, 2026 | Apr 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 14, 2026 | May 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2026 | Apr 24, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2026 | Apr 20, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 23, 2026 | In progress | In Progress |
Structural plan approval Building Inspection · PAD-STR | Apr 23, 2026 | Apr 24, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Aug 10, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2026 | Aug 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2026 | Aug 12, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2026 | Aug 13, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2026 | Sep 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2026 | Sep 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2026 | Oct 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2026 | Oct 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 14, 2026 | Oct 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 19, 2026 | Oct 27, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 22, 2026 | Oct 22, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1,900,000
| Name | Role | License on permit |
|---|---|---|
| Stephen Sedgwick Sutro Sutro Architects | Architect | C30702 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023