443 Fair Oaks St
San Francisco permit 202512222384 · Mission
Horizontal addition of less than 15% of unit size rear. convert storage area to garage, new curb cut. re-build 2-story rear portion of structure. convert portion of 2nd unit to primary unit garage entry vestible.
- Filed
- Jan 20, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 19, 2025 | Jan 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Oct 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Mar 10, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Mar 10, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Feb 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 21, 2026 | Feb 25, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Feb 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | May 12, 2026 | May 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2026 | May 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2026 | Oct 7, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 25, 2026 | Sep 25, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 25, 2026 | Oct 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 25, 2026 | Sep 25, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Sep 25, 2026 | Oct 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2026 | Oct 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 5, 2026 | Oct 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 20, 2026 | Oct 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 20, 2026 | Oct 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 20, 2026 | Oct 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2026 | Oct 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| David George Yama Yama Architecture | Architect | C32627 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022