40 Clifford Tr
San Francisco permit 202512222390 · Castro/Upper Market
Convert attic space into habitable space, add two dormers. attic space will add 1-bedroom and 1-bathroom. add fire sprinklers to entire bldg.
- Filed
- May 14, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- 7 times, by Planning, Permit Center, Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 22, 2025 | Dec 22, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 22, 2025 | Dec 22, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 5, 2026 | Feb 11, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 12, 2026 | Mar 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2026 | Mar 12, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 13, 2026 | Apr 3, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2026 | May 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2026 | May 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 14, 2026 | May 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2026 | Jul 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2026 | Jul 14, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2026 | Jun 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2026 | May 18, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 28, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 14, 2026 | Oct 27, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | May 28, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 31, 2026 | Aug 31, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 22, 2026 | Sep 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 13, 2026 | Oct 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 14, 2026 | Oct 26, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 14, 2026 | Oct 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 14, 2026 | Oct 15, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 14, 2026 | Oct 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Jacqueline Ching Yan Law Jac Law Studio | Architect | C32350 |
| Kathryn Briggs Base Design | Engineer | S5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022