1590 A Union St
San Francisco permit 202512222424 · Marina
Convert 2/f office space (1590a) to state adu (1 bed & 1 bath) 750sf. remodel (e) kitchen with new cabinets, appliances and finishes. remodel bathroom, new vent, new finishes and fixtures. new wiring and lighting throughout. new washer/dryer in-unit.
- Filed
- Jan 8, 2026
- Issued
- May 22, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 27 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2025 | Jan 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2026 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 16, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 13, 2026 | Jan 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Jan 26, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | May 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 24, 2026 | Apr 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 24, 2026 | Apr 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2026 | Apr 1, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 24, 2026 | Mar 25, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2026 | Mar 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 24, 2026 | Apr 14, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2026 | Mar 26, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 24, 2026 | Apr 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2026 | May 4, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Apr 24, 2026 | Apr 29, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 29, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | May 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 28, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 12, 2026 | May 13, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 14, 2026 | May 22, 2026 | Administrative |
Address verification Building Inspection · ADDR | May 21, 2026 | May 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $86,800
| Name | Role | License on permit |
|---|---|---|
| Mike Patrick Larkin Mike Larkin Architecture | Architect | C25214 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026