1701 Yosemite Av
San Francisco permit 202512232467 · Bayview Hunters Point
To comply with nov#: 202538869. in-kind repairs to restaurant at 1st level and residential unit at second level (due to fire) with accesibility upgrades.
- Filed
- Dec 23, 2025
- Issued
- Oct 30, 2026 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 23, 2025 | Dec 23, 2025 | Administrative |
Code enforcement Building Inspection · CES | Dec 23, 2025 | Dec 23, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Dec 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Jan 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Jan 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 13, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Mar 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 4, 2026 | Mar 4, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 4, 2026 | Mar 4, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 4, 2026 | Mar 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 20, 2026 | Apr 20, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 20, 2026 | Apr 20, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 20, 2026 | Apr 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2026 | Apr 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 22, 2026 | Apr 22, 2026 | Approved |
Public health review Public Health · HEALTH | Apr 22, 2026 | Apr 22, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Apr 22, 2026 | Apr 22, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 8, 2026 | May 8, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | May 8, 2026 | May 8, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 20, 2026 | May 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 29, 2026 | May 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2026 | Oct 30, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $480,000
| Name | Role | License on permit |
|---|---|---|
| Abraham Christopher Lynn Degenkolb Engineers | Architect | C84331 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026