1875 48th Av
San Francisco permit 202512232509 · Sunset/Parkside
Convert(e) rear portion of the lvl 1 into new adu (exclude garage). interior remodel at lvl 2 with interior stair relocation. new rear deck. new heat pump and tankless water heater. new lighting and electrical outlets per plan.
- Filed
- Jan 12, 2026
- Issued
- May 28, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 29 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 21, 2025 | Jan 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2026 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Feb 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Feb 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Feb 2, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Jan 27, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jan 13, 2026 | Jan 24, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 13, 2026 | Feb 14, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 23, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | May 21, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 30, 2026 | Apr 8, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 30, 2026 | Apr 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2026 | Apr 1, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 30, 2026 | Apr 8, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 30, 2026 | May 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 1, 2026 | May 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 1, 2026 | Apr 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 1, 2026 | Apr 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2026 | May 7, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 6, 2026 | May 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2026 | May 8, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | May 6, 2026 | May 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 6, 2026 | May 7, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 6, 2026 | May 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2026 | May 8, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 20, 2026 | May 20, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 21, 2026 | May 28, 2026 | Administrative |
Address verification Building Inspection · ADDR | May 26, 2026 | May 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Chiawang Yeh Chiawang Structural Eng | Engineer | S5164 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2019