556 Mississippi St
San Francisco permit 202512242602 · Potrero Hill
Raise roof of (e) 3/f & add bathroom. convert 2/f bath to office, relocate laundry, remodel half-bath and add tub. reinforce g/f retaining walls.
- Filed
- Jan 21, 2026
- Issued
- Nov 3, 2026 (9 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 22, 2025 | Jan 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Apr 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Mar 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Mar 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2026 | Feb 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Feb 3, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | Aug 27, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 10, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 16, 2026 | Mar 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 8, 2026 | May 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2026 | May 19, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 8, 2026 | May 19, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 8, 2026 | May 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2026 | Jul 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2026 | May 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 28, 2026 | May 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jun 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 28, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Aug 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Aug 25, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Aug 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2026 | Aug 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2026 | Aug 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2026 | Aug 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2026 | Nov 3, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $225,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey S Gainer Actual-Size Architecture | Architect | C27762 |
| Erik Mcgregor Wmstructural | Engineer | S6802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022