2400 Noriega St
San Francisco permit 202512242623 · Sunset/Parkside
No physical alterations to the building. permit amends the permitted occupancy to allow for an accessory use occupancy e approvied under planning record 2024-001865cua planning commission motion no. 21756
- Filed
- Jan 14, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 14 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 24, 2025 | Dec 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 24, 2025 | Dec 24, 2025 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Dec 28, 2025 | Jan 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 15, 2026 | Jan 21, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Feb 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2026 | Feb 19, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Jan 27, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 15, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Feb 4, 2026 | Feb 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Kok Jin Yeo | Architect | C83626 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026