295 La Avanzada St
San Francisco permit 202512242629 · Twin Peaks
Erect a 3 story,9 dwelling bldg with 1 basement. type v-a
- Filed
- Feb 9, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 33 stops across 7 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department, Public Utilities, Planning
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2025 | Jan 6, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 7, 2026 | Jan 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2026 | Feb 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Mar 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Mar 12, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 10, 2026 | Mar 25, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 20, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 10, 2026 | Mar 2, 2026 | Approved |
Public Health HEALTH-AW | Feb 10, 2026 | Feb 25, 2026 | Administrative |
Public Health HEALTH-MH | Feb 10, 2026 | Feb 19, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Feb 10, 2026 | In progress | In Progress |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 6, 2026 | Mar 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2026 | Mar 17, 2026 | Not Applicable |
Address verification Building Inspection · ADDR | May 14, 2026 | May 14, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | May 14, 2026 | Jun 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2026 | Jun 8, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2026 | May 14, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | May 14, 2026 | May 19, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 15, 2026 | May 15, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 15, 2026 | May 15, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 21, 2026 | Jul 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 21, 2026 | Jul 23, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 21, 2026 | Jul 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2026 | Jul 23, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 21, 2026 | Aug 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 27, 2026 | Jul 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Oct 23, 2026 | Nov 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2026 | Oct 28, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Filed
- Estimated cost
- $4,900,000
| Name | Role | License on permit |
|---|---|---|
| Riyad N Ghannam Rg-Architecture | Architect | C29116 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2021