3646 21st St
San Francisco permit 202512242644 · Castro/Upper Market
Erect 4-story over basement, type vb, 2-unit residential building.
- Filed
- Jan 14, 2026
- Issued
- Apr 16, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 44 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Works, Public Utilities, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 22, 2025 | Jan 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2026 | Jan 15, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 15, 2026 | Feb 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Feb 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Jan 23, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 15, 2026 | Jan 22, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 15, 2026 | Feb 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Jan 28, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jan 15, 2026 | Jan 28, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 15, 2026 | In progress | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2026 | Feb 5, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Feb 18, 2026 | Feb 18, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Mar 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Mar 19, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 3, 2026 | Mar 10, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2026 | Mar 12, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Mar 3, 2026 | Mar 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 5, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 3, 2026 | Mar 5, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Mar 19, 2026 | Mar 26, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 26, 2026 | Apr 16, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2026 | Apr 16, 2026 | Administrative |
Addendum 1: Grading, shoring, excavation & foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 30, 2026 | May 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 12, 2026 | Jun 12, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 12, 2026 | Aug 7, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 12, 2026 | Aug 6, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jun 12, 2026 | Jun 16, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2026 | Jun 16, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 12, 2026 | Jul 26, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2026 | Jun 24, 2026 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 12, 2026 | Jun 24, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jun 12, 2026 | Oct 5, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2026 | Aug 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 20, 2026 | Sep 9, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 14, 2026 | Sep 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 21, 2026 | Sep 23, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2026 | Sep 23, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 21, 2026 | Oct 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2026 | Sep 23, 2026 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 23, 2026 | Sep 23, 2026 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2026 | In progress | In Progress |
Addendum 2: Final: superstructure, steel frame, architectural & t-24/mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 6, 2026 | Oct 27, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 27, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,500,000
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican & Mosey Architects | Architect | C31398 |
| Arne Halterman | Engineer | S5090 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2019