819 V Alabama St

San Francisco permit 202512262672 · Mission

New buildingFull plan reviewFiled
Street view · Jan 2023
Google Street View of 819 V Alabama St, Jan 2023
Scope of work
As written on the permit application.

Erect 4-story 2 unit + 2 adu type 3a residential building. scope has changed to build an r2.

Timeline
Key dates from the city record.
Filed
Mar 26, 2026
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
44 stops across 6 departments
Comments issued
20 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works, Public Utilities
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 16, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Mar 13, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Mar 31, 2026Administrative

Zoning review

Planning · CP-ZOC

Apr 7, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Apr 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Apr 24, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 29, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 8, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 2, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Jun 5, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 14, 2026Issued Comments

Public Utilities programs review

Public Utilities · SFPUC-PRG

Apr 16, 2026Approved

Permit Processing Center

Building Inspection · PPC

In progress—

Mechanical plan review quality control

Building Inspection · MECH-QC

Apr 28, 2026Approved

Electrical plan review

Building Inspection · MECH-E

May 5, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 24, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Jun 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 3, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 14, 2026Issued Comments

Building plan review

Building Inspection · BLDG

Sep 2, 2026Approved

Zoning review

Planning · CP-ZOC

Oct 16, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Sep 18, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 4, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Sep 4, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 14, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Sep 10, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 18, 2026Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Sep 14, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Sep 17, 2026Administrative

Building Inspection

MECH-E-QC

Oct 27, 2026Administrative

Zoning review

Planning · CP-ZOC

In progress—

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

Nov 3, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 27, 2026Approved

Fire prevention review

Fire Department · SFFD

Nov 3, 2026Approved

Street use and mapping

Public Works · DPW-BSM

Oct 27, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 4, 2026Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Oct 30, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 4, 2026Approved

Street use and mapping

Public Works · DPW-BSM

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Filed
Estimated cost
$2,400,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Peiman Ghaffari

S & P Structural Engineers

ArchitectC-97150
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512262672 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record