551 26th Av
San Francisco permit 202512262711 · Outer Richmond
Replace (e) generator, belly tank, concrete pad, & exhaust piping in rear yard w/ new in same location. replace ats inside building with new ats. remove (e) interior window and fill-in opening to match (e) partition. provide new accessible restroom signage at (e) single user restroom.
- Filed
- Dec 26, 2025
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 8, 2026 | Jan 29, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 11, 2026 | Feb 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2026 | Aug 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 27, 2026 | Sep 22, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2026 | Nov 3, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2026 | Sep 21, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 27, 2026 | Oct 19, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 27, 2026 | Oct 19, 2026 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Aug 27, 2026 | Sep 3, 2026 | Approved |
Public Health HEALTH-HM | Aug 27, 2026 | Aug 28, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 27, 2026 | In progress | — |
Building Inspection MECH-E-QC | Sep 8, 2026 | Sep 8, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2026 | Sep 21, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 19, 2026 | Oct 19, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 19, 2026 | Oct 19, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 19, 2026 | Oct 19, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filing
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Vito K Vanoni San Francisco Public Works | Authorized agent-others | c27134 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019