3153 17th St
San Francisco permit 202512262714 · Mission
Alteration and change of use of an (e) 14,320sf. building with an 5,684sf addition for dance studios and support spaces. new 3rd lv performance space and 1,508sf rooftop terrace (590sf occupiable). scope includes limited improvements at 3153 17th st as well as interconnections between the two
- Filed
- Dec 26, 2025
- Issued
- Jul 24, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 45 stops across 7 departments
- Comments issued
- 7 times, by Public Utilities, Public Works, Public Health, Fire Department, Building Inspection
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 20, 2026 | May 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 21, 2026 | May 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2026 | Jul 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 21, 2026 | Jul 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2026 | May 28, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 21, 2026 | May 30, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2026 | May 29, 2026 | Issued Comments |
Public Health HEALTH-MH | May 21, 2026 | May 21, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 21, 2026 | Jul 17, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 29, 2026 | May 29, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2026 | Jun 26, 2026 | Approved |
Public Health HEALTH-MH | Jun 24, 2026 | Jul 2, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 26, 2026 | Jun 26, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 8, 2026 | Jul 8, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2026 | Jul 13, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 13, 2026 | Jul 16, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2026 | Jul 24, 2026 | Administrative |
Addendum 1: Demo foundation/super structure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Sep 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 9, 2026 | Sep 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 9, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Oct 16, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2026 | Sep 15, 2026 | Issued Comments |
Public Health HEALTH-MH | Sep 9, 2026 | Sep 10, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 9, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2026 | Oct 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Architecture/mep1
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2026 | Sep 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Sep 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Sep 9, 2026 | Sep 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Sep 9, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2026 | Oct 7, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2026 | Oct 15, 2026 | Approved |
Public Health HEALTH-MH | Sep 9, 2026 | Sep 22, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 9, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2026 | Sep 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2026 | Oct 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $141,046
| Name | Role | License on permit |
|---|---|---|
| Peter Wright Pfau Perkins & Will | Architect | C21794 |
| Michael Paul Gemmill Nabih Youssef Associats | Engineer | 4703 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023