150 Oak St
San Francisco permit 202512292848 · Hayes Valley
Ab-004 priority phase 2.2: non-structural int ti-establish staff-operated cafe serving hs students on 6th flr. limited to int arch finishes &typical mep modifications. cafe provide pre-pared, non-cooked food & bev only; no cooking equip, hooods or special ventilation of fp req. student/faculty will
- Filed
- Dec 29, 2025
- Issued
- May 20, 2026 (5 months after filing)
- Completed
- Nov 3, 2026 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2025 typically took 5 months to be issued (median of 642 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department, Public Utilities, Public Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 23, 2025 | Jan 15, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 15, 2026 | Jan 15, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 15, 2026 | Feb 17, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2026 | Feb 20, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 15, 2026 | Jan 21, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Feb 12, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 15, 2026 | Feb 4, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 15, 2026 | May 19, 2026 | Administrative |
Public health food review Public Health · HEALTH-FD | Feb 5, 2026 | Feb 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 24, 2026 | Feb 24, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 31, 2026 | Apr 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2026 | Apr 3, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 31, 2026 | Apr 9, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Mar 31, 2026 | Apr 1, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2026 | Apr 3, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Mar 31, 2026 | Mar 31, 2026 | Issued Comments |
Public health food review Public Health · HEALTH-FD | Apr 17, 2026 | Apr 17, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2026 | Apr 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2026 | May 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 19, 2026 | May 20, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Joshua Sawyer Cohn Ca Architects | Architect | C23410 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025