150 Oak St

San Francisco permit 202512292849 · Hayes Valley

OtherFull plan reviewComplete
Street view · Apr 2025
Google Street View of 150 Oak St, Apr 2025
Scope of work
As written on the permit application.

Ab-004 priority phase 2c: voluntary & selective renovation of (e) mep systems serving approx 125,400 gsf of the 177,800 gsf of entire (e) bldg. proposed mep design will supplement current arch & struc ti. non-seismic struc work ltd to addition of penthouse rooftop support & anchorage of mech equip.

Timeline
Key dates from the city record.
Filed
Feb 20, 2026
Issued
Apr 30, 2026 (2 months after filing)
Completed
Nov 3, 2026 (6 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
21 stops across 4 departments
Comments issued
7 times, by Permit Center, Building Inspection, Fire Department
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 15, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Feb 17, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 18, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 12, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 27, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Mar 12, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 23, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 27, 2026Not Applicable

Permit Processing Center

Building Inspection · PPC

Apr 29, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Feb 20, 2026Administrative

Building plan review

Building Inspection · BLDG

Apr 23, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 15, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 20, 2026Issued Comments

Electrical plan review

Building Inspection · MECH-E

Apr 16, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 20, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 24, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 27, 2026Approved

Electrical plan review

Building Inspection · MECH-E

Apr 23, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 27, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 30, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$16,200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Joshua Sawyer Cohn

Ca Architects

ArchitectC23410
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512292849 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record