142 Anderson St
San Francisco permit 202512292881 · Bernal Heights
1/f re-setback of front face, with new entry door and re-building of stairs. 1/f replacement of concrete slab, with addition of french drains. 1/f new bathroom and hobby room habitable spaces. 2/fl side in-filling at rear with renovation of bathroom and kitchen. rebuilding rear stairs
- Filed
- Mar 3, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Public Utilities, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 22, 2025 | Jan 6, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2026 | Mar 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 3, 2026 | Apr 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 3, 2026 | Apr 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 3, 2026 | Apr 23, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2026 | Mar 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 3, 2026 | Mar 9, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2026 | Mar 23, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 3, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Aug 17, 2026 | Aug 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 17, 2026 | Aug 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2026 | Sep 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 17, 2026 | Aug 20, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2026 | Aug 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Chung Chi Ly | Engineer | C79958 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025