250 Arleta Av
San Francisco permit 202512292888 · Visitacion Valley
New 1-story addition at rear with 2-bedrooms and roof deck to (e) sfr.
- Filed
- Jan 12, 2026
- Issued
- Jul 15, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 31 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 29, 2025 | Jan 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2026 | Jan 13, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2026 | Jan 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2026 | Mar 27, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2026 | Feb 25, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2026 | Feb 18, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 13, 2026 | Jan 20, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2026 | Jan 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2026 | Jan 30, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 13, 2026 | Jul 9, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Jan 14, 2026 | Feb 18, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Feb 27, 2026 | Feb 27, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 23, 2026 | Mar 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 23, 2026 | Apr 6, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 23, 2026 | Mar 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Mar 23, 2026 | Apr 10, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2026 | Mar 25, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 23, 2026 | Apr 21, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 23, 2026 | Apr 2, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 27, 2026 | Mar 27, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 13, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 17, 2026 | Jun 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 17, 2026 | Jul 9, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2026 | Jun 18, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2026 | Jun 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 17, 2026 | Jun 18, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2026 | Jul 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 17, 2026 | Jun 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2026 | Jun 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 18, 2026 | Jun 22, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 9, 2026 | Jul 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $286,340
| Name | Role | License on permit |
|---|---|---|
| Mark Elliott Bucciarelli Baukunst | Architect | C23159 |
| William Wei-Qiang Liang William Liang | Engineer | S5157 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2015