250 Arleta Av

San Francisco permit 202512292888 · Visitacion Valley

AdditionFull plan reviewIssued
Street view · Jun 2015
Google Street View of 250 Arleta Av, Jun 2015
Scope of work
As written on the permit application.

New 1-story addition at rear with 2-bedrooms and roof deck to (e) sfr.

Timeline
Key dates from the city record.
Filed
Jan 12, 2026
Issued
Jul 15, 2026 (6 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 6 departments
Comments issued
6 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 12, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jan 13, 2026Administrative

Zoning review

Planning · CP-ZOC

Jan 15, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 27, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 25, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 18, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 20, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 14, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 30, 2026Approved

Permit Processing Center

Building Inspection · PPC

Jul 9, 2026Administrative

Urban forestry

Public Works · DPW-BUF

Feb 18, 2026Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Feb 27, 2026Approved

Zoning review

Planning · CP-ZOC

Mar 25, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Apr 6, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 24, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 10, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Mar 25, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 21, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 2, 2026Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 27, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 13, 2026Approved

Zoning review

Planning · CP-ZOC

Jun 17, 2026Approved

Building plan review

Building Inspection · BLDG

Jul 9, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 18, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 23, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 18, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2026Approved

Urban forestry

Public Works · DPW-BUF

Jun 26, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 24, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 22, 2026Administrative

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$286,340
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Elliott Bucciarelli

Baukunst

ArchitectC23159
William Wei-Qiang Liang

William Liang

EngineerS5157
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512292888 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record