2280 31st Av
San Francisco permit 202512302954 · Sunset/Parkside
Convert 1/f (e) storage & partial gargae into living area. new 36in stairs & handrails.new kitchen layout and (n) dining rm on 2/f. infill lightwell for new bathroom layout. lower proposed living area on 1/f via excavate.
- Filed
- Jan 21, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 21 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 29, 2025 | Jan 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2026 | Jan 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 21, 2026 | Mar 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2026 | Mar 25, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2026 | Mar 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 21, 2026 | Jan 27, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Jan 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2026 | Feb 10, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 21, 2026 | Jul 10, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Mar 25, 2026 | Mar 25, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2026 | Mar 26, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 26, 2026 | Mar 26, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 27, 2026 | May 22, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 24, 2026 | Jun 25, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 30, 2026 | Jun 30, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jun 30, 2026 | Jul 1, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 1, 2026 | Jul 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2026 | Jul 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2026 | Jul 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 10, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $320,502
| Name | Role | License on permit |
|---|---|---|
| Samuel Kwong Arcus Architecture & Planning | Architect | C14679 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022