As written on the permit application.

Additions to rear of house at first, second, and third floor. new stair to connect first and second floors, convert rear storage space to office, reconfigure and remodel third floor bathrooms and closets.

Timeline
Key dates from the city record.
Filed
Feb 6, 2026
Issued
Jul 7, 2026 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 6 departments
Comments issued
4 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 12, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 9, 2026Administrative

Permit Processing Center

Building Inspection · PPC

Jun 8, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 10, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 23, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 23, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Mar 19, 2026Approved

Fire prevention review

Fire Department · SFFD

Feb 18, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 11, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 19, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 30, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 30, 2026Approved-Stipulated

Fire prevention review

Fire Department · SFFD

May 1, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 7, 2026Approved

Building plan review

Building Inspection · BLDG

May 8, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

May 15, 2026Approved

Zoning review

Planning · CP-ZOC

May 19, 2026Approved

Building plan review

Building Inspection · BLDG

May 21, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

May 21, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 1, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 21, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 22, 2026Approved

Fire prevention review

Fire Department · SFFD

Jun 1, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Jul 7, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$230,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Judith Ann Mattingly

Mattingly Thaler Archit.

ArchitectC23854
Robert Eric Smith

Smithworks Engineering

EngineerS5679
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202512302970 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record