579 05th Av
San Francisco permit 202512302975 · Inner Richmond
Comply w/nov 202538644 & 202542838, rebuild 3-flrs fire damaged bldg (unit 579 & 579a). unit 579: add new bathroom & family room @ 1/f, replace 2-fixture bath w/ 3-fixture @ 1/f, add wetbar @ 1/f, replace tub w/shower @ 2/f. unit 579a: ext kitchen/living/dining to bdrm #3, replace tub w/shower @ 3/f
- Filed
- Feb 15, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 5 departments
- Comments issued
- 5 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 29, 2025 | Jan 16, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 2, 2026 | Feb 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2026 | Feb 17, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Feb 17, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Feb 18, 2026 | Feb 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Apr 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2026 | Apr 6, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2026 | Mar 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 26, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2026 | Mar 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 10, 2026 | Aug 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2026 | Aug 14, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2026 | Aug 20, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2026 | Aug 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2026 | Aug 12, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Aug 14, 2026 | Aug 14, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Nov 4, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Nov 4, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Nov 4, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $168,000
| Name | Role | License on permit |
|---|---|---|
| Jian Hao Huang Hao Engineering & Consulting | Engineer | 87110 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015