633 Chestnut St
San Francisco permit 202512302989 · North Beach
3rd flr remodel: infill lightwell, remodel kitchen, laundry, baths, convert bedroom to walk in closet.
- Filed
- Dec 30, 2025
- Issued
- May 4, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2025 were typically issued within 1 month (median of 5,178 issued permits).
- Review stops
- 7 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 30, 2025 | Dec 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 30, 2025 | Dec 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 30, 2025 | Dec 30, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 30, 2025 | Dec 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2026 | Jan 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2026 | Jan 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 4, 2026 | May 4, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Aaron Michael Lim Aaron Lim Design | Architect | C37034 |
| Erik Mcgregor Wmstructural | Engineer | S6802 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025