2041 Fulton St
San Francisco permit 202512303001 · Lone Mountain/USF
Interior remodel: lightwell expansion, structural upgrades, hvac/plumbing/electrical upgrades; window/door replacement. new roof deck; new framed deck extending off the office inthe side yard setback. new interior stairs to level 2; ev charging stations. lightwell in-fill.1 new bathroom in each unit
- Filed
- Feb 20, 2026
- Issued
- Oct 28, 2026 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 39 stops across 5 departments
- Comments issued
- 11 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 30, 2025 | Dec 30, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 30, 2025 | Dec 30, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 26, 2026 | Feb 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2026 | Feb 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 25, 2026 | Mar 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Apr 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Apr 13, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2026 | Mar 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Mar 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2026 | Mar 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 25, 2026 | Oct 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 23, 2026 | Jul 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 23, 2026 | Jul 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2026 | Jul 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2026 | Jul 27, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2026 | Jul 30, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2026 | Aug 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Aug 21, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2026 | Aug 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 20, 2026 | Aug 24, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2026 | Sep 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 24, 2026 | Sep 4, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 8, 2026 | Sep 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 8, 2026 | Sep 10, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2026 | Sep 11, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 8, 2026 | Sep 10, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2026 | Sep 9, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 10, 2026 | Sep 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2026 | Sep 11, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 29, 2026 | Oct 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2026 | Oct 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2026 | Oct 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2026 | Sep 30, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2026 | Oct 1, 2026 | Approved |
Zoning review Planning · CP-ZOC | Oct 9, 2026 | Oct 20, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2026 | Oct 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 9, 2026 | Oct 15, 2026 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 9, 2026 | Oct 19, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2026 | Oct 28, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Hallie Chen Caha Design Group | Architect | C38753 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025