15 Park Hill Av
San Francisco permit 202512303034 · Castro/Upper Market
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev 201908068086-s1 & 202508213586:horizontal expanding at g/f to include a bedroom and play room. new g/f deck and stairs to garden below. and new deck above g/f horizontal expansion for floor 2.new stairs from floor 2 deck to g/f deck below. new crawl space storage beneath horizontal g/f addition.
- Filed
- Feb 6, 2026
- Issued
- Aug 17, 2026 (6 months after filing)
- Completed
- Not completed yet
- Review stops
- 33 stops across 6 departments
- Comments issued
- 11 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 19, 2025 | Jan 8, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2026 | Feb 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2026 | Feb 6, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 6, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 6, 2026 | Mar 25, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 6, 2026 | Mar 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2026 | Mar 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2026 | Feb 11, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2026 | Feb 12, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2026 | Feb 18, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 6, 2026 | Aug 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 23, 2026 | Jul 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2026 | May 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 23, 2026 | May 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2026 | Apr 27, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 23, 2026 | May 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2026 | Apr 27, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2026 | May 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2026 | May 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 1, 2026 | Jul 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 1, 2026 | Jul 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 1, 2026 | Jul 6, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 1, 2026 | Jul 9, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2026 | Jul 9, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 31, 2026 | Aug 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2026 | Aug 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 31, 2026 | Aug 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2026 | Aug 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 31, 2026 | Aug 6, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 31, 2026 | Aug 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2026 | Aug 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2026 | Aug 17, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Suspend
- Estimated cost
- $162,997
| Name | Role | License on permit |
|---|---|---|
| Kamala L Mostert Mostert Architecture | Architect | C26896 |
| Shaun Edward Moynahan Semco Engineering | Engineer | S4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025