163 V Rae Av #0
San Francisco permit 202601143853 · Outer Mission
Recognition of (e) upper 3rd lvl adu unit #165 in an (e) 3-story sfd. main unit #163 on lower 2 lvls includes ground lvl kitchenette and proposed partitioned front bedroom with front window replacement.
- Filed
- Mar 25, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 22 stops across 6 departments
- Comments issued
- 4 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2026 | Jan 26, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 10, 2026 | Mar 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2026 | Mar 26, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 26, 2026 | Mar 30, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 26, 2026 | Apr 21, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 26, 2026 | Apr 2, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 26, 2026 | Mar 30, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 26, 2026 | Mar 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 26, 2026 | May 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 26, 2026 | Apr 8, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 26, 2026 | In progress | Administrative |
Zoning review Planning · CP-ZOC | Mar 27, 2026 | Mar 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2026 | Aug 24, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 25, 2026 | Aug 25, 2026 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Sep 2, 2026 | Sep 3, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 2, 2026 | Sep 2, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 2, 2026 | Sep 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2026 | Sep 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 2, 2026 | Sep 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2026 | Sep 4, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Sep 25, 2026 | Sep 25, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $355,195
| Name | Role | License on permit |
|---|---|---|
| Sheldon Errol Eaton Vicinity Architects | Architect | C36656 |
| Della Tran Della Tran | Engineer | 91229 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019