249 21st Av
San Francisco permit 202601164041 · Outer Richmond
Alter interior floor plan of g/f & top floor. addition limited to rear of building. no change to bldg height or in unit count. new deck at building rear. fill-in nw 3/f corner & extend habitable space 6'. add habitable space in (e) garage.
- Filed
- Feb 16, 2026
- Issued
- Sep 10, 2026 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 16, 2026 | Jan 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 16, 2026 | Jan 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 20, 2026 | Jan 20, 2026 | Approved |
Intake Building Inspection · INTAKE | Jan 22, 2026 | Jan 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 22, 2026 | Jan 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 22, 2026 | Jan 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2026 | Feb 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2026 | Jan 27, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 29, 2026 | Feb 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2026 | Feb 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 18, 2026 | Feb 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 18, 2026 | Apr 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2026 | Apr 7, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2026 | Mar 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Feb 18, 2026 | Feb 24, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2026 | Feb 20, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 18, 2026 | Sep 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 30, 2026 | Apr 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 30, 2026 | May 18, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2026 | May 15, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 30, 2026 | Jun 4, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2026 | May 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | May 28, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 8, 2026 | Jun 8, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 6, 2026 | Jul 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 6, 2026 | Jul 8, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2026 | Jul 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 6, 2026 | Jul 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 10, 2026 | Jul 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 10, 2026 | Jul 14, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2026 | Jul 10, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 17, 2026 | Jul 17, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | Aug 24, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 26, 2026 | Sep 1, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2026 | Aug 31, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 26, 2026 | Sep 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2026 | Sep 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Sep 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $560,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey J Burris Studio 12 Architecture | Architect | C27594 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025