25 Forest Side Av
San Francisco permit 202601214255 · West of Twin Peaks
Rear 3rd story attic conversion for primary suite.living,dining,kitchen layout at the 2/f.alteration of the (e) stair to a code-compliant stair at all levels.removal of pre-existing illegal kitchen at the lower level family room.kitchen area to be replaced with a wet bar.deck guardrail replacement
- Filed
- Feb 20, 2026
- Issued
- Jun 26, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 29 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 16, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2026 | Feb 23, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 23, 2026 | Feb 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 23, 2026 | Apr 13, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 23, 2026 | Apr 9, 2026 | Not Applicable |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2026 | Mar 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 23, 2026 | Feb 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2026 | Feb 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2026 | Mar 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 23, 2026 | Jun 9, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Apr 2, 2026 | Apr 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2026 | Apr 16, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 2, 2026 | Apr 15, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2026 | Apr 8, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 2, 2026 | Apr 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 28, 2026 | Apr 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 28, 2026 | May 19, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2026 | May 7, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 28, 2026 | May 7, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2026 | May 1, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | May 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | May 26, 2026 | May 26, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | May 27, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 26, 2026 | Jun 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 26, 2026 | May 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 26, 2026 | May 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 26, 2026 | Jun 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 9, 2026 | Jun 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2026 | Jun 26, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $798,000
| Name | Role | License on permit |
|---|---|---|
| Renato M Jose Renato Jose I Architect | Architect | C28111 |
| David Benjamin Yadegar David Yadegar, Pe | Engineer | C73922 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022