524 Central Av
San Francisco permit 202601234440 · Lone Mountain/USF
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 202404260881 remove structural work @ 3rd fl front unit; front unit layout to remain unchanged. structural work removed was approved under voluntary seismic strengthening, ref (202404260881 and 202111303291)
- Filed
- Jan 23, 2026
- Issued
- Feb 11, 2026 (within 1 month of filing)
- Completed
- Not completed yet
- Review stops
- 5 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jan 23, 2026 | Jan 23, 2026 | Administrative |
Intake Building Inspection · INTAKE | Jan 23, 2026 | Jan 23, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2026 | Jan 23, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jan 23, 2026 | Jan 23, 2026 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2026 | Feb 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Chiawang Yeh Chiawang Structural Eng | Engineer | S5164 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025