538 Peralta Av
San Francisco permit 202601234463 · Bernal Heights
Create j-adu on 1/f garage (271sf). move washer/dryer from 1/f garage to 2/f kitchen. j-adu will have sep w/d.
- Filed
- Feb 11, 2026
- Issued
- Jun 1, 2026 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Public Works, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2026 | Feb 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2026 | Feb 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2026 | Feb 27, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Feb 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2026 | Feb 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2026 | Feb 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 12, 2026 | Mar 3, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Feb 19, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 12, 2026 | May 21, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 4, 2026 | Mar 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 7, 2026 | Apr 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 7, 2026 | Apr 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 7, 2026 | Apr 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2026 | Apr 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 7, 2026 | Apr 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2026 | Apr 13, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 7, 2026 | Apr 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2026 | Apr 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 28, 2026 | May 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 28, 2026 | May 5, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2026 | May 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 28, 2026 | May 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 28, 2026 | May 7, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2026 | Apr 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 28, 2026 | May 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2026 | May 5, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 7, 2026 | May 7, 2026 | Approved |
Development fee collection Building Inspection · DFCU | May 18, 2026 | May 19, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 21, 2026 | Jun 1, 2026 | Administrative |
Address verification Building Inspection · ADDR | Jun 1, 2026 | Jun 1, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $115,206
| Name | Role | License on permit |
|---|---|---|
| Ethan C Andersen Drafting Cafe Architects | Architect | C34235 |
| Matthew Bryan Tropp Tropp Consulting Engineers | Engineer | S5683 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025