524 Post St
San Francisco permit 202601274614 · Nob Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to bpa: 202411134879 - to add / replace cooler with fountain. (inspection found water fountain not on original plans)
- Filed
- Jan 27, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 7 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 27, 2026 | Jan 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 27, 2026 | Jan 27, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Filed
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Carmen Marianne Pauli Heritage Architecture | Architect | C28831 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025