95 Santa Paula Av
San Francisco permit 202601284717 · West of Twin Peaks
Interior remodel with new kitchen, 2 new bathrooms, replace windows/doors in-kind per st. francis wood hoa guidelines/approval letter. convert 583 sf of (e) space to an adu per ca state program. note: electrical permit to upgrade pg&e service & panel, add recessed lights, ground outlets is opened.
- Filed
- Feb 10, 2026
- Issued
- Apr 7, 2026 (2 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 26 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 27, 2026 | Feb 9, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2026 | Feb 10, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 10, 2026 | Feb 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Mar 5, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2026 | Mar 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2026 | Feb 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 10, 2026 | Feb 17, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 10, 2026 | Feb 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 10, 2026 | Mar 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 10, 2026 | Feb 17, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 10, 2026 | Apr 1, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 20, 2026 | Mar 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2026 | Mar 23, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 20, 2026 | Mar 23, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2026 | Mar 27, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 20, 2026 | Mar 24, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2026 | Mar 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2026 | Mar 26, 2026 | Approved |
Zoning review Planning · CP-ZOC | Mar 30, 2026 | Mar 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 30, 2026 | Mar 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 30, 2026 | Mar 30, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Mar 30, 2026 | Mar 31, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 30, 2026 | Apr 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 30, 2026 | Mar 30, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Apr 1, 2026 | Apr 1, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2026 | Apr 7, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $385,000
| Name | Role | License on permit |
|---|---|---|
| James Francis Knowles Street Capitolo Knowles Llp | Engineer | C50651 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025