Vertical addition of 4th story and stair to upper unit, 152 liberty, addition of (n) roof deck at 4th floor, sprinkler entire building with nfpa 13r system on seperate permit, full seismic upgrade.

Timeline
Key dates from the city record.
Filed
Feb 2, 2026
Issued
May 4, 2026 (3 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 6 departments
Comments issued
5 times, by Building Inspection, Public Works
Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 10, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 17, 2026Administrative

Zoning review

Planning · CP-ZOC

Feb 23, 2026Approved

Building plan review

Building Inspection · BLDG

Mar 20, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 20, 2026Administrative

Mechanical and energy plan review

Building Inspection · MECH

Mar 13, 2026Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 19, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Feb 23, 2026Issued Comments

Urban forestry

Public Works · DPW-BUF

Mar 9, 2026Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 4, 2026Approved

Permit Processing Center

Building Inspection · PPC

May 1, 2026Administrative

Street use and mapping

Public Works · DPW-BSM

Mar 26, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 1, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 9, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 7, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 2, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 9, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 23, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 1, 2026Approved

Zoning review

Planning · CP-ZOC

Apr 30, 2026Approved

Building plan review

Building Inspection · BLDG

Apr 27, 2026Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 28, 2026Approved

Fire prevention review

Fire Department · SFFD

Apr 24, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 29, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 30, 2026Approved

Central Permit Bureau

Building Inspection · CPB

May 4, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$362,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Nilgun Asci Wolpe

N. Y Engineering

Engineer68482
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202602024994 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record