1573 34th Av
San Francisco permit 202602035142 · Sunset/Parkside
New 3rd story vertical addition to (e) sfd and interior remodel @ 1st & 2md story to include: remodel & expand (e) kitchen, and 2 (e) bathjs, new primary bedroom and abath, new windows @ addition, (e)courtyard and rear elevation, replace (e) foundation for new clg hgt @ 1st story, new structural
- Filed
- Feb 12, 2026
- Issued
- Jul 15, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 32 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 2, 2026 | Feb 6, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2026 | Feb 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 12, 2026 | Feb 17, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2026 | Apr 8, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2026 | Mar 31, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2026 | Mar 26, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 12, 2026 | Feb 23, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 19, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Feb 12, 2026 | Mar 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2026 | Mar 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 12, 2026 | Jul 2, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2026 | Mar 19, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 6, 2026 | Apr 8, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 7, 2026 | May 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2026 | May 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 7, 2026 | May 15, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2026 | Jun 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 7, 2026 | May 15, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 7, 2026 | May 14, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 7, 2026 | May 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2026 | May 14, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | May 20, 2026 | May 20, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 16, 2026 | Jun 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 16, 2026 | Jun 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 16, 2026 | Jun 16, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2026 | Jul 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 16, 2026 | Jun 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2026 | Jun 24, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 16, 2026 | Jun 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2026 | Jun 17, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jun 25, 2026 | Jun 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2026 | Jul 15, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $906,978
| Name | Role | License on permit |
|---|---|---|
| Ross Harlen Levy Levy Art & Architecture | Architect | C25660 |
| Shaun Edward Moynahan Semco Engineering Inc. | Engineer | S-4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015