2440 Pacific Av #0
San Francisco permit 202602045186 · Pacific Heights
Renovate primary suite
- Filed
- Mar 11, 2026
- Issued
- Jun 11, 2026 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- 3 times, by Planning, Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 4, 2026 | Feb 4, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 4, 2026 | Feb 11, 2026 | Issued Comments |
Intake Building Inspection · INTAKE | Feb 12, 2026 | Feb 12, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 13, 2026 | Feb 13, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2026 | Feb 18, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2026 | Mar 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2026 | Mar 11, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 11, 2026 | Mar 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 11, 2026 | Apr 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2026 | Apr 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 11, 2026 | Mar 20, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2026 | Mar 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 11, 2026 | May 27, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 6, 2026 | May 27, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2026 | May 12, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2026 | May 15, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 6, 2026 | May 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2026 | May 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 27, 2026 | Jun 11, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $250,000
| Name | Role | License on permit |
|---|---|---|
| Suzette Anne Smith Suzette Smith Inc | Architect | C30980 |
| Kris Wallace Johnson Gfds Engineers | Engineer | 4319 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015