2262 Pine St
San Francisco permit 202602045246 · Pacific Heights
Addition and interior alts: 2-story rear yard addition. remodel to (e) kitchens and bathrooms. new bathrom on 1/f & 2/f. structural changes to basement only.
- Filed
- Feb 25, 2026
- Issued
- Aug 19, 2026 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 13 times, by Building Inspection, Fire Department, Public Works, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 3, 2026 | Feb 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2026 | Feb 25, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Feb 25, 2026 | Mar 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Apr 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Apr 16, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2026 | Apr 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Apr 16, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 25, 2026 | Feb 26, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 25, 2026 | Apr 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 25, 2026 | Mar 16, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 25, 2026 | Aug 12, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Apr 29, 2026 | Apr 29, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | May 28, 2026 | May 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2026 | Jun 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2026 | Jun 8, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 28, 2026 | Jul 22, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 28, 2026 | Jun 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 28, 2026 | Jun 15, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2026 | Jun 5, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 29, 2026 | Jun 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 29, 2026 | Jul 9, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 29, 2026 | Jul 9, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 29, 2026 | Jul 9, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 29, 2026 | Jul 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 29, 2026 | Jul 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jul 10, 2026 | Jul 10, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 10, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2026 | Jul 13, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2026 | Jul 10, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 14, 2026 | Jul 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 14, 2026 | Jul 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 21, 2026 | Jul 21, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 22, 2026 | Jul 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 5, 2026 | Aug 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 5, 2026 | Aug 8, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2026 | Aug 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 5, 2026 | Aug 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2026 | Aug 6, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 5, 2026 | Aug 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2026 | Aug 11, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2026 | Aug 11, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Aug 12, 2026 | Aug 12, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2026 | Aug 19, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Val Larry Dizitser Western Design Co | Engineer | C55483 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025