260 Avila St
San Francisco permit 202602105593 · Marina
Interior renovation - relocate kitchen and bathrooms, new skylights, replace windows, new front door and garage door. no change to height or bulk.
- Filed
- Mar 18, 2026
- Issued
- Aug 5, 2026 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2026 typically took 4 months to be issued (median of 245 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2026 | Feb 23, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 4, 2026 | Mar 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2026 | Mar 18, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 19, 2026 | Jul 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2026 | Apr 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2026 | Apr 26, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2026 | Apr 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 19, 2026 | Mar 20, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2026 | Apr 9, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 19, 2026 | Jul 31, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2026 | Jul 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 29, 2026 | Jun 29, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2026 | Jul 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 14, 2026 | Jul 14, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 15, 2026 | Jul 22, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jul 22, 2026 | Jul 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2026 | Jul 31, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2026 | Aug 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $797,405
| Name | Role | License on permit |
|---|---|---|
| Martin C Kellogg | Architect | C35171 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022