112 Ellsworth St
San Francisco permit 202602105596 · Bernal Heights
Renovation of a single-family residence.windows & garage door to be replaced @ front facade.non-code compliant front stairs & structurally compromised front retaining wall to be replaced.gable roof to be extended to rear wall @ existing height.
- Filed
- Jul 27, 2026
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 24 stops across 6 departments
- Comments issued
- 7 times, by Permit Center, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2026 | Feb 20, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jul 3, 2026 | Jul 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 27, 2026 | Jul 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 28, 2026 | Jul 31, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 28, 2026 | Aug 26, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 28, 2026 | Aug 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2026 | Aug 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 28, 2026 | Aug 11, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2026 | Jul 30, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 28, 2026 | Sep 16, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2026 | Aug 13, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 28, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2026 | Sep 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 29, 2026 | Sep 30, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2026 | Oct 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 29, 2026 | Oct 15, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2026 | Oct 5, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2026 | Sep 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2026 | Sep 30, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 29, 2026 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2026 | Oct 1, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Lawrence Tik Man Wong L Wong Engineering | Engineer | 5135 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025